How contractors can reduce FF&E risk on education projects

Author Image

Author: Mark Allen

Date: November 03, 2026

When a contractor delivers a new school, college or learning space, the final stages of the build can be challenging. Several trades need access, unfinished areas can delay progress, and a fixed completion date leaves little room for manoeuvre.

For the furniture, fixtures and equipment (FF&E) team, this often means less time to complete an installation, which can impact the contractor’s schedule and costs.

‘The end date often doesn’t move very far, but our programme often gets compressed,’ says Mark Allen, Operations Director at Pinnacle. ‘The risk there is that we don’t have enough time to complete our installation.’